Vero Beach Airport (VRB) is undergoing transformative capital projects to improve the property for commercial and industrial development. If you're interested in learning more about our capital projects, please contact Airport Operations Manager Brandon Dambeck at bdambeck@covb.org

VRB Capital Projects

  1. Construct Natural Gas Pipeline – Construction completed.

  2. Reconstruct Center Apron – Construction completed.

  3. Rehabilitate GA Apron – Construction completed.

  4. Rehabilitate Runway 12R/30L – Construction completed.

  5. Construct Hangar Ramp – Construction completed.

  6. Terminal Building Generator – Pending construction.

  7. Airport Facility Air Condition Replacement – Pending construction.

  8. Rehabilitate Airport Terminal Building (Design and Construct, Phase 1) – Pending design and construction.

  9. Redevelop Commercial Park (Phase 1) – Portions of project completed. 

  10. Airfield Marking Project – Construction complete.

  11. Airport Wayfinding Signage – Pending construction.

  12. Rehabilitate Southwest Apron - Design complete. 

  13. Airport Master Plan Update – Ongoing. For more information, click here

  14. Airport Stormwater Plan – Pending FAA grant offer. 

  15. Terminal Sterile Area Improvements – Pending design and construction.

  16. Sweeper Truck – Pending grant offer.

  17. ARFF Vehicle – Pending design and bid. 

  18. Airport Fiber Telecommunications Backbone – Pending

  19. Rehabilitate Taxiway Bravo (Design) – Pending

  20. Construct GA Apron – Pending

  21. Rehabilitate Taxiway Bravo (Construct) – Pending

  22. Rehabilitate Airport Terminal Building (Construct, Phase 2) – Pending

  23. Redevelop Commercial Park (Phase 2) – Pending

  24. Extend Taxiway Bravo (EA and Design) – Pending

  25. Rehabilitate Airport Drainage System – Pending

  26. Extend Taxiway Bravo (Construct) – Pending

  27. Extend/Mark/Light Taxiway Echo West of Runway 4 (EA and Design) – Pending

  28. Extend/Mark/Light Taxiway Echo West of Runway 4 (Construct) – Pending

  29. Terminal Parking Lot – Pending

  30. Airfield Electrical Improvements – Pending